To establish a baseline going forward we commissioned a thorough professional inspection of all existing infrastructure. Based on the resulting inspection reports we’ve been able to determine which structures need to be replaced and what remedial work should be undertaken on the remaining structures. The plan consists of three phases:

1) completion of three unfinished projects: the stupa, lama’s cabin and the bath house; basic electrical system upgrades; renovation of the barn to accommodate community programs; exterior repairs.

2) further electrical system upgrades; upgrading roads and parking areas; upgrading foundations and drainage of existing structures; renovation of existing structures; demolition and site preparation.

3) new construction: multi-purpose building with kitchen, office and staff accommodation; meditation hall; new yurt platform; six additional meditation kutis.